Request to relax Apollo LEM qualification requirements rejected

ASPO Manager Joseph F. Shea informed Grumman that a proposal they had made during the LEM Program Review on July 6 regarding broader qualification scheduling and parts deviations had been reviewed by NASA and it was considered "not in the best interests of the program to relax the requirements to the extent proposed by GAEC.

"

Shea cited a paragraph of the Contract Technical Specification which specified: "Qualification tests supporting a particular flight vehicle shall be completed prior to that vehicle being delivered from the Contractor."

It was NASA's desire that LEM program scheduling be such that all ground test logic constraints required in support of launch dates would be completed at least six weeks prior to scheduled launch dates. Shea pointed out that the LEM program schedules as presented by Grumman at the July 6 Review were not in complete accord with dates previously provided June 7 in a datafax signed by Shea.

Shea required the following delivery dates from Grumman: LEM-1, November 15, 1966; LEM-2, February 15, 1967; LEM-3, April 15, 1967; LEM-4, July 15, 1967; LEM-5, October 15, 1967; LEM-6, December 15, 1967; LEM-7, February 15, 1968; LEM-8, April 15, 1968; LEM-9, June 15, 1968; LEM-10, August 15, 1968; and LEM-11, October 15, 1968.

Grumman was requested to provide NASA, no later than August 2, 1965, their plan for support of a LEM program development schedule which would incorporate these requirements.


Home - Search - Browse - Alphabetic Index: 0- 1- 2- 3- 4- 5- 6- 7- 8- 9
A- B- C- D- E- F- G- H- I- J- K- L- M- N- O- P- Q- R- S- T- U- V- W- X- Y- Z
© 1997-2017 Mark Wade - Contact
© / Conditions for Use