Gemini home
topic index
Gemini preflight
Credit - NASA
Manufacturer's Designation: McDonnell-Douglas. Class: Manned. Type: Spacecraft. Destination: Maximum Payload Orbit. Nation: USA. Agency: NASA. Manufacturer: McDonnell.

It was obvious to NASA that there was a big gap of three to four years between the last Mercury flight and the first scheduled Apollo flight. There would therefore be no experience in the US in understanding the problems of orbital maneuvering, rendezvous, docking, lifting re-entry, and space walking before the Apollo flights, which required all of these to be successfully accomplished to complete the lunar landing mission. Gemini began as Mercury Mark II to fill this gap.

The concept was to enlarge the Mercury capsule's basic design to accommodate two crew, provide it with orbital maneuvering capability, use existing boosters to launch it and an existing upper rocket stage as a docking target. The latest aircraft engineering was exploited , resulting in a modularized design that provided easy access to and changeout of equipment mounted external to the crew's pressure vessel.

In many ways the Gemini design was ahead of that of the Apollo, since the project began two years later . The crew station layout was similar to that of the latest military fighters; the capsule was equipped with ejection seats, inertial navigation, the pilot's traditional 8-ball attitude display, and radar. The escape tower used for Mercury was deleted; the propellants used in the Titan II launch vehicle, while toxic, corrosive, poisonous, and self-igniting, did not explode in the manner of the Atlas or Saturn LOX/Kerosene combination. The ejection seats served as the crew escape method in the lower atmosphere, just as in a high-performance aircraft. The seats were also needed for the original landing mode, which involved deployment of a huge inflated Rogallo wing (ancestor of today's hang gliders) with a piloted landing on skids at Edwards Dry Lake. In the event, the wing could not be made to deploy reliably before flights began, so the capsule made a parachute-borne water landing, much to the astronauts' chagrin.

All around the Gemini was considered the ultimate 'pilot's spacecraft', and it was also popular with engineers because of its extremely light weight. The capsule allowed recover of a crew of two for only 50% more than the Mercury capsule weight, and half of the weight per crew member of the Apollo design. The penalty was obvious - it was christened the 'Gusmobile' since diminutive Gus Grissom was the only astronaut who was said to be able to fit into it. The crew member was crammed in, shoulder to shoulder with his partner, his helmet literally scrunched against the hatch, which could be opened for space walks. With the crew unable to fully stretch out unless an EVA was scheduled, living in the capsule was literally painful on the long missions (Gemini 5 and 7). Getting back into the seat and getting the hatch closed in an inflated suit in zero gravity was problematic and would have been impossible if the spacewalking astronaut was incapacitated in even a minor way.

Early on it was proposed that the Gemini could be used for manned circumlunar or lunar missions at a fraction of the cost and much earlier than Apollo. Truth be told, a Gemini launched atop a Titan 3E or Saturn IVB Centaur could have accomplished a circumlunar flight as early as 1966 and, using earth orbit rendezvous techniques, a landing at least a year before Apollo. But the capsule, while perhaps suited as a ferry vehicle to space stations, would have been quite marginal for the lunar mission due to the cramped accommodation. But mainly NASA was fully committed to the Apollo program, which was grounded on a minimum three man crew and minimum 10,000 pound command module weight.

At a cost of 5% of the Apollo project, NASA staged twelve flights, ten of them manned, in the course of which the problems of rendezvous, docking, and learning how to do work in a spacesuit in zero-G were tackled and solved. It was said that not much of this was fed back to Apollo, since the two projects had completely different sets of contractors and there was little cross-fertilization in the rendezvous and docking areas. But it was undeniable that important issues in regard to working in zero-G were discovered and solved and both flight and ground crews gained experience that would make the Apollo flights successful.

Gemini was to have continued to fly into the 1970's as the return capsule of the USAF Manned Orbiting Laboratory program. However with the MOL's cancellation in 1969 work at McDonnell came to an end and the last models of the finest spacecraft ever built were scrapped.

Full Details of the Gemini spacecraft and its subsystems could be seen at:

Gemini Spacecraft Description

Gemini Subsystem Development Diaries

Unit Cost $: 13.000 million. Crew Size: 2. Typical orbit: 246 km circular orbit, 30.2 deg inclination. Length: 5.67 m (18.60 ft). Maximum Diameter: 3.05 m (10.00 ft). Habitable Volume: 2.55 m3. Mass: 3,851 kg (8,490 lb). RCS Impulse: 1,168 kgf-sec. Main Engine Thrust: 706 N (158 lbf). Main Engine Propellants: N2O4/MMH. Main Engine Propellants: 455 kg (1,003 lb). Main Engine Isp: 273 sec. Spacecraft delta v: 98 m/s (321 ft/sec). Electrical System: Fuel Cells. Electric System: 2.16 average kW. Electric System: 151.00 kWh.

  • Gemini RMOther Designations: Reentry Module. Part of: Gemini. Class: Manned. Type: Spacecraft Module.

    Crew Size: 2. Length: 3.35 m (10.99 ft). Basic Diameter: 2.32 m (7.61 ft). Maximum Diameter: 2.32 m (7.61 ft). Habitable Volume: 2.55 m3. Mass: 1,983 kg (4,371 lb). Structure Mass: 638 kg (1,406 lb). Heat Shield Mass: 144 kg (317 lb). Reaction Control System: 133 kg (293 lb). Recovery Equipment: 98 kg (216 lb). Navigation Equipment: 62 kg (136 lb). Telemetry Equipment: 51 kg (112 lb). Electrical Equipment: 125 kg (275 lb). Communications Systems: 26 kg (57 lb). Crew Seats and Provisions: 426 kg (939 lb). Crew mass: 144 kg (317 lb). Miscellaneous Contingency: 99 kg (218 lb). RCS Fine No x Thrust: 16 x 98 N. RCS Propellants: N2O4/MMH. RCS Isp: 283 sec. RCS Impulse: 90 kgf-sec. Main Engine Propellants: N2O4/MMH. Main Engine Propellants: 33 kg (72 lb). Main Engine Isp: 283 sec. L/D Hypersonic: 0.16. Electrical System: Batteries. Electric System: 4.00 kWh. Battery: 180.00 Ah.

  • Gemini AMOther Designations: Adapter Module. Part of: Gemini. Class: Manned. Type: Spacecraft Module.

    Length: 0.92 m (3.01 ft). Basic Diameter: 2.59 m (8.49 ft). Maximum Diameter: 2.59 m (8.49 ft). Mass: 591 kg (1,302 lb). Structure Mass: 160 kg (350 lb). Reaction Control System: 200 kg (440 lb). RCS Coarse No x Thrust: 6 x 420 N. RCS Isp: 273 sec. Main Engine: 131 kg (288 lb). Main Engine Propellants: Solid. Main Engine Propellants: 100 kg (220 lb). Main Engine Isp: 255 sec. Spacecraft delta v: 101 m/s (331 ft/sec).

  • Gemini EMOther Designations: Equipment Module. Part of: Gemini. Class: Manned. Type: Spacecraft Module.

    Length: 1.40 m (4.50 ft). Basic Diameter: 3.05 m (10.00 ft). Maximum Diameter: 3.05 m (10.00 ft). Mass: 1,277 kg (2,815 lb). Structure Mass: 250 kg (550 lb). Reaction Control System: 60 kg (132 lb). Telemetry Equipment: 40 kg (88 lb). Electrical Equipment: 294 kg (648 lb). Miscellaneous Contingency: 75 kg (165 lb). Environmental Control System: 117 kg (257 lb). RCS Fine No x Thrust: 8 x 98 N. RCS Propellants: N2O4/MMH. RCS Isp: 288 sec. RCS Impulse: 1,078 kgf-sec. Main Engine: 120 kg (260 lb). Main Engine Propellants: N2O4/MMH. Main Engine Propellants: 322 kg (709 lb). Main Engine Isp: 273 sec. Spacecraft delta v: 222 m/s (728 ft/sec). Electrical System: Fuel Cells. Electric System: 2.16 average kW. Electric System: 151.00 kWh.


Gemini Chronology
  • 1958 January 1 - NASA sketches two-crew Mercury follow-on spacecraft - Program: Gemini. Launch Vehicle: Atlas.
    In 1958 H. Kurt Strass and Caldwell C. Johnson of NASA's Space Task Group at Langley Field, Virginia.sketched a spacecraft design concept for a two-man orbiting laboratory to be launched by an Atlas-Vega booster. This was one of the earliest sketches of a two-crew Mercury follow-on. The Vega stage was dropped in favour of the Agena a year later, and a similar one-crew Mercury-Agena space station was proposed by McDonnell some years later.

  • 1959 April 1 - Two-man Mercury capsule proposed. -
    H. Kurt Strass of the Space Task Group (STG) at Langley Field, Virginia described some preliminary ideas of STG planners regarding a follow-on to Mercury: (1) an enlarged Mercury capsule to place two men in orbit for three days; (2) a two-man Mercury capsule and a large cylindrical structure to support a two-week mission. (In its 1960 budget, NASA had requested $2 million to study methods of constructing a manned orbiting laboratory or converting the Mercury spacecraft into a two-man laboratory for extended space missions.) Additional Details: Two-man Mercury capsule proposed..

  • 1959 April 24 - NASA budgets for research on techniques and problems of space rendezvous. - Program: Gemini.
    DeMarquis D. Wyatt, Assistant to the Director of Space Flight Development, testified before Congress in support of NASA's request for $3 million in Fiscal Year 1960 for research on techniques and problems of space rendezvous. Wyatt explained that logistic support for a manned space laboratory, a possible post-Mercury flight program, depended upon resolving several key problems and making rendezvous in orbit practical. Among key problems he cited were establishment of methods for fixing the relative positions of two objects in space; development of accurate target acquisition devices to enable supply craft to locate the space station; development of guidance systems to permit precise determination of flight paths; and development of reliable propulsion systems for maneuvering in orbit.

  • 1959 June 22 - Preliminary design of a two-man space laboratory. - Program: Gemini.
    H. Kurt Strass of Space Task Group's Flight Systems Division (FSD) recommended the establishment of a committee to consider the preliminary design of a two-man space laboratory. Representatives from each of the specialist groups within FSD would work with a special projects group, the work to culminate in a set of design specifications for the two-man Mercury.

  • 1960 April 5 - Modification of Mercury spacecraft for a controlled reentry begun. - Program: Mercury.
    The Space Task Group notified the Ames Research Center that preliminary planning for the modification of the Mercury spacecraft to accomplish controlled reentry had begun, and Ames was invited to participate in the study. Preliminary specifications for the modified spacecraft were to be ready by the end of the month. This program was later termed Mercury Mark II and eventually Project Gemini.

  • 1960 May 16 - Representatives of NASA's research centers gathered at Langley Research Center to present papers on current programs related to space rendezvous and to discuss possible future work on rendezvous. -
    During the first day of the conference, papers were read on the work in progress at Langley, Ames, Lewis, and Flight Research Centers, Marshall Space Flight Center, and Jet Propulsion Laboratory. The second day was given to a roundtable discussion. All felt strongly that rendezvous would soon be essential, that the technique should be developed immediately, and that NASA should make rendezvous experiments to develop the technique and establish the feasibility of rendezvous.

  • 1960 June 1 - Space Task Group (STG) issued a set of guidelines for advanced manned space flight programs. -
    The document comprised five papers presented by STG personnel at a series of meetings with personnel from NASA Headquarters and various NASA field installations during April and May. Primary focus was a manned circumlunar mission, or lunar reconnaissance, but in his summary, Charles J. Donlan, Associate Director (Development), described an intermediate program that might fit into the period between the phasing out of Mercury and the beginning of flight tests of the multimanned vehicle. During this time, 'it is attractive to consider the possibility of a flight-test program involving the reentry unit of the multimanned vehicle which at times we have thought of as a lifting Mercury.' What form such a vehicle might take was uncertain, but it would clearly be a major undertaking; much more information was needed before a decision could be made. To investigate some of the problems of a reentry vehicle with a lift-over-drag ratio other than zero, STG had proposed wind tunnel studies of static and dynamic stability, pressure, and heat transfer at Langley, Arnold Engineering Development Center, and Ames facilities.

  • 1961 January 5 - NASA's Space Exploration Program Council discusses manned lunar landing. -
    NASA's Space Exploration Program Council met in Washington to discuss manned lunar landing. Among the results of the meeting was an agreement that NASA should plan an earth-orbital rendezvous program independent of, although contributing to, the manned lunar program.

  • 1961 January 20 - Space Task Group management discusses a follow-on Mercury program. - Program: Gemini.
    Space Task Group management held a Capsule Review Board meeting. The first topic on the agenda was a follow-on Mercury program. Several types of missions were considered, including long-duration, rendezvous, artificial gravity, and flight tests of advanced equipment. Major conclusion was that a follow-on program needed to be specified in greater detail.

  • 1961 February 13 - Beginning of Gemini - Program: Gemini. Launch Vehicle: Titan.
    First formal NASA/McDonnell discussions on Mercury Mark II (Gemini).

  • 1961 February 13 - NASA and McDonnell began discussions of an advanced Mercury spacecraft. - Program: Gemini.
    McDonnell had been studying the concept of a maneuverable Mercury spacecraft since 1959. On February 1, Space Task Group (STG) Director Robert R. Gilruth assigned James A. Chamberlin, Chief, STG Engineering Division, who had been working with McDonnell on Mercury for more than a year, to institute studies with McDonnell on improving Mercury for future manned space flight programs. Additional Details: NASA and McDonnell began discussions of an advanced Mercury spacecraft..

  • 1961 May 5 - Integrated research, development, and applied orbital operations program to cost $1 billion through 1970. - Program: Gemini.
    A NASA Headquarters working group, headed by Bernard Maggin, completed a staff paper presenting arguments for establishing an integrated research, development, and applied orbital operations program at an approximate cost of $1 billion through 1970. The group identified three broad categories of orbital operations: inspection, ferry, and orbital launch. It concluded that future space programs would require an orbital operations capability and that the development of an integrated program, coordinated with Department of Defense, should begin immediately. The group recommended that such a program, because of its scope and cost, be independent of other space programs and that a project office be established to initiate and implement the program.

  • 1961 May 8 - Martin briefed NASA on the Titan II weapon system. - Program: Gemini. Launch Vehicle: Titan.
    Martin Company personnel briefed NASA officials in Washington, D.C., on the Titan II weapon system. Albert C. Hall of Martin had contacted NASA's Associate Administrator, Robert C. Seamans, Jr., on April 7 to propose the Titan II as a launch vehicle for a lunar landing program. Although skeptical, Seamans nevertheless arranged for a more formal presentation. Abe Silverstein, NASA Director, Office of Space Flight Programs, was sufficiently impressed by the Martin briefing to ask Director Robert R. Gilruth and Space Task Group to study possible Titan II uses. Silverstein shortly informed Seamans of the possibility of using the Titan II to launch a scaled-up Mercury spacecraft.

  • 1961 May 17 - Design Study of a Manned Spacecraft Paraglide Landing System. -
    Space Task Group (STG) issued a Statement of Work for a Design Study of a Manned Spacecraft Paraglide Landing System. The purpose of the study was to define and evaluate problem areas and to establish the design parameters of a system to provide spacecraft maneuverability and controlled energy descent and landing by aerodynamic lift. McDonnell was already at work on a modified Mercury spacecraft; the proposed paraglide study was to be carried on concurrently to allow the paraglide landing system to be incorporated as an integral subsystem. STG Director Robert R. Gilruth requested that contracts for the design study be negotiated with three companies which already had experience with the paraglide concept: Goodyear Aircraft Corporation, Akron, Ohio; North American Aviation, Inc., Space and Information Systems Division, Downey, California; and Ryan Aeronautical Company, San Diego, California. Each contract would be funded to a maximum of $100,000 for a study to be completed within two and one-half months from the date the contract was awarded. Gilruth expected one of these companies subsequently to be selected to develop and manufacture a paraglide system based on the approved design concept. In less than three weeks, contracts had been awarded to all three companies. Before the end of June, the design study formally became Phase I of the Paraglider Development Program.

  • 1961 June 9 - Chamberlin briefed NASA Headquarters on McDonnell's advanced capsule design. -
    James A. Chamberlin, Chief, Engineering Division, Space Task Group (STG), briefed Director Robert R. Gilruth, senior STG staff members, and George M. Low and John H. Disher of NASA Headquarters on McDonnell's advanced capsule design. The design was based on increased component and systems accessibility, reduced manufacturing and checkout time, easier pilot insertion and emergency egress procedures, greater reliability, and adaptability to a paraglide landing system. It departed significantly from Mercury capsule design in placing most components outside the pressure vessel and increasing retrograde and posigrade rocket performance. The group was reluctant to adopt what seemed to be a complete redesign of the Mercury spacecraft, but it decided to meet again on June 12 to review the most desirable features of the new design. After discussing most of these items at the second meeting, the group decided to ask McDonnell to study a minimum-modification capsule to provide an 18-orbit capability.

  • 1961 July 7 - McDonnell studies of the redesigned Mercury spacecraft. - Program: Gemini. Launch Vehicle: Atlas.
    Walter F. Burke of McDonnell summarized the company's studies of the redesigned Mercury spacecraft for Space Task Group's senior staff. McDonnell had considered three configurations: (1) the minimum-change capsule, modified only to improve accessibility and handling, with an adapter added to carry such items as extra batteries; (2) a reconfigured capsule with an ejection seat installed and most of the equipment exterior to the pressure vessel on highly accessible pallets; and (3) a two-man capsule, similar to the reconfigured capsule except for the modification required for two rather than one-man operation. The capsule would be brought down on two Mercury-type main parachutes, the ejection seat serving as a redundant system. In evaluating the trajectory of the two-man capsule, McDonnell used Atlas Centaur booster performance data.

  • 1961 July 27 - Advanced Mercury concepts - Program: Mercury. Flight: Mercury MA-10, Mercury MA-11, Mercury MA-12.
    After the 2-man space concept (later designated Project Gemini) was introduced in May 1961, a briefing between McDonnell and NASA personnel was held on the matter. As a result of this meeting, space flight design effort was concentrated on the 18-orbit 1-man Mercury and on a 2-man spacecraft capable of advanced missions.

  • 1961 July 27 - Representatives of NASA and McDonnell met to decide what course McDonnell's work on the advanced Mercury should take. -
    The result: McDonnell was to concentrate all its efforts on two versions of the advanced spacecraft. The first required minimum changes; it was to be capable of sustaining one man in space for 18 orbits. The second, a two-man version capable of advanced missions, would require more radical modifications.

  • 1961 August 1 - McDonnell proposal for Gemini - Program: Gemini.
    Baseline 10 earth orbit flights; also proposed for docking with Centaur and circumlunar flights by March 1965. NASA not interested - threat to Apollo.

  • 1961 August 14 - Report on Mercury Mark II. -
    Fred J. Sanders and three other McDonnell engineers arrived at Langley Research Center to help James A. Chamberlin and other Space Task Group (STG) engineers who had prepared a report on the improved Mercury concept, now known as Mercury Mark II. Then, with the assistance of Warren J. North of NASA Headquarters Office of Space Flight Programs, the STG group prepared a preliminary Project Development Plan to be submitted to NASA Headquarters. Although revised six times before the final version was submitted on October 27, the basic concepts of the first plan remained unchanged in formulating the program.

  • 1961 August 31 - Chamberlain proposes lunar landing by Gemini - Program: Apollo. Launch Vehicle: Saturn C-3.
    Landing by Gemini using 4,000 kg wet/680 kg empty lander and Saturn C-3 booster. Landing by January 1966.

  • 1961 October 1 - Titan II to be selected as the launch vehicle for NASA's advanced Mercury. - Launch Vehicle: Titan.
    Martin Company received informal indications from the Air Force that Titan II would be selected as the launch vehicle for NASA's advanced Mercury. Martin, Air Force, and NASA studied the feasibility of modifying complex 19 at Cape Canaveral from the Titan weapon system configuration to the Mercury Mark II launch vehicle configuration.

  • 1961 October 27 - Program of manned spaceflight for 1963-1965. - Launch Vehicle: Atlas, Titan.
    Space Task Group (STG), assisted by George M. Low, NASA Assistant Director for Space Flight Operations, and Warren J. North of Low's office, prepared a project summary presenting a program of manned spaceflight for 1963-1965. This was the final version of the Project Development Plan, work on which had been initiated August 14. Additional Details: Program of manned spaceflight for 1963-1965..

  • 1961 October 27 - James A. Chamberlin expects approval of the Mark II spacecraft program within 30 days. -
    James A. Chamberlin, Chief of Space Task Group (STG) Engineering Division, expecting approval of the Mark II spacecraft program within 30 days, urged STG Director Robert R. Gilruth to begin reorienting McDonnell, the proposed manufacturer, to the new program. To react quickly once the program was approved, McDonnell had to have an organization set up, personnel assigned, and adequate staffing ensured. Chamberlin suggested an amendment to the existing letter contract under which McDonnell had been authorized to procure items for Mercury Mark II. This amendment would direct McDonnell to devote efforts during the next 30 days to organizing and preparing to implement its Mark II role.

  • 1961 November 1 - Space Task Group's Engineering Division briefed Seamans on the Mercury Mark II proposal. -
    Space Task Group's Engineering Division Chief James A. Chamberlin and Director Robert R. Gilruth briefed NASA Associate Administrator Robert C. Seamans, Jr., at NASA Headquarters on the Mercury Mark II proposal. Specific approval was not granted, but Chamberlin and Gilruth left Washington convinced that program approval would be forthcoming.

  • 1961 November 15 - McDonnell submitted to Manned Spacecraft Center the detail specification of the Mercury Mark II spacecraft. -
    A number of features closely resembled those of the Mercury spacecraft. Among these were the aerodynamic shape, tractor rocket escape tower, heatshield, impact bag to attenuate landing shock, and the spacecraft-launch vehicle adapter. Salient differences from the Mercury concept included housing many of the mission-sustaining components in an adapter that would be carried into orbit rather than being jettisoned following launch, bipropellant thrusters to effect orbital maneuvers, crew ejection seats for emergency use, onboard navigation system (inertial platform, computers, radar, etc.), and fuel cells as electrical power source in addition to silver-zinc batteries. The long-duration mission was viewed as being seven days.

  • 1961 November 20 - North American to proceed with the Paraglider Development Program. - Program: Gemini.
    Manned Spacecraft Center notified North American to proceed with Phase II-A of the Paraglider Development Program. A letter contract, NAS 9-167, followed on November 21; contract negotiations were completed February 9, 1962; and the final contract was awarded on April 16, 1962. Phase I, the design studies that ran from the beginning of June to mid-August 1961, had already demonstrated the feasibility of the paraglider concept. Phase II-A, System Research and Development, called for an eight-month effort to develop the design concept of a paraglider landing system and to determine its optimal performance configuration. This development would lay the groundwork for Phase II, Part B, comprising prototype fabrication, unmanned and manned flight testing, and the completion of the final system design. Ultimately Phase III-Implementation-would see the paraglider being manufactured and pilots trained to fly it.

  • 1961 November 20 - Milton W. Rosen, Director of Launch Vehicles and Propulsion in NASA's Office of Manned Space Flight, presented recommendations on rendezvous to D. Brainerd Holmes, Director of Manned Space Flight. -
    The working group Rosen chaired had completed a two-week study of launch vehicles for manned spaceflight, examining most intensively the technical and operational problems posed by orbital rendezvous. Because the capability for rendezvous in space was essential to a variety of future missions, the group agreed that 'a vigorous high priority rendezvous development effort must be undertaken immediately.' Its first recommendation was that a program be instituted to develop rendezvous capability on an urgent basis.

  • 1961 November 28 - Phase II-A of the Paraglider Development Program discussed. -
    Representatives of the Space and Information Systems Division of North American, Langley Research Center, Flight Research Center (formerly High Speed Flight Station), and Manned Spacecraft Center met to discuss implementing Phase II-A of the Paraglider Development Program. They agreed that paraglider research and development would be oriented toward the Mercury Mark II project and that paraglider hardware and requirements should be compatible with the Mark II spacecraft. Langley Research Center would support the paraglider program with wind tunnel tests. Flight Research Center would oversee the paraglider flight test program. Coordination of the paraglider program would be the responsibility of Manned Spacecraft Center.

  • 1961 December 5 - Recommendation that the weapon system of the Titan II, with minimal modifications, be approved for the Mercury Mark II rendezvous mission. - Launch Vehicle: Titan.
    On the basis of a report of the Large Launch Vehicle Planning Group, Robert C. Seamans, Jr., NASA Associate Administrator, and John H. Rubel, Department of Defense Deputy Director for Defense Research and Engineering, recommended to Secretary of Defense Robert S. McNamara that the weapon system of the Titan II, with minimal modifications, be approved for the Mercury Mark II rendezvous mission. The planning group had first met in August 1961 to survey the Nation's launch vehicle program and was recalled in November to consider Titan II, Titan II-1/2, and Titan III. On November 16, McNamara and NASA Administrator James E. Webb had also begun discussing the use of Titan II.

  • 1961 December 6 - Robert R. Gilruth, Director of the Manned Spacecraft Center, transmitted the procurement plan for the Mark II spacecraft to NASA Headquarters for approval. -
    This included scope of work, plans, type of contract administration, contract negotiation and award plan, and schedule of procurement actions. At Headquarters, D. Brainerd Holmes, Director of Manned Space Flight, advised Associate Administrator Robert C. Seamans, Jr., that the extended flight would be conducted in the last half of calender year 1963 and that the rendezvous flight tests would begin in early 1964. Because of short lead time available to meet the Mark II delivery and launch schedules, it was requested that fiscal year 1962 funds totaling $75.8 million be immediately released to Manned Spacecraft Center in preparation for the negotiation of contracts for the spacecraft and for the launch vehicle modifications and procurements.

  • 1961 December 7 - DOD/NASA coordination for Mercury Mark II - Program: Gemini. Launch Vehicle: Titan.
    NASA Associate Administrator Robert C. Seamans, Jr., and DOD Deputy Director of Defense Research and Engineering John H. Rubel recommended to Secretary of Defense Robert S. McNamara and NASA Administrator James E. Webb that detailed arrangements for support of the Mercury Mark II spacecraft and the Atlas-Agena vehicle used in rendezvous experiments be planned directly between NASA's Office of Manned Space Flight and the Air Force and other DOD organizations. NASA's primary responsibilities would be the overall management and direction for the Mercury Mark II/ Agena rendezvous development and experiments. The Air Force responsibilities would include acting as NASA contractor for the Titan II launch vehicle and for the Atlas-Agena vehicle to be used in rendezvous experiments. DOD's responsibilities would include assistance in the provision and selection of astronauts and the provision of launch, range, and recovery support, as required by NASA.

  • 1961 December 7 - Two-man Mercury Mark II spacecraft announced - Program: Gemini. Launch Vehicle: Titan.
    Plans for the development of a two-man Mercury spacecraft were announced by Robert R. Gilruth, MSC Director. The two-man spacecraft, to be built by McDonnell Aircraft Corporation, would be similar in shape to the Mercury spacecraft but slightly larger and two to three times heavier. Its booster rocket would be a modified Air Force Titan II, scheduled for flight test in early 1962. One of the major objectives in the program would be a test of orbital rendezvous, in which the two-man spacecraft would be launched into orbit by the Titan II and attempt to rendezvous with an Agena stage launched by an Atlas rocket. The total cost for a dozen two-man spacecraft plus boosters and other equipment was estimated at $500 million.

  • 1961 December 7 - NASA Associate Administrator Robert C. Seamans, Jr., approved the Mark II project development plan. -
    The document approved was accompanied by a memorandum from Colonel Daniel D. McKee of NASA Headquarters stressing the large advances possible in a short time through the Mark II project and their potential application in planned Apollo missions, particularly the use of rendezvous techniques to achieve manned lunar landing earlier than direct ascent would make possible.

  • 1961 December 7 - NASA announced plans to develop a two-man Mercury capsule. - Program: Gemini. Launch Vehicle: Atlas, Titan.
    In Houston, Director Robert R. Gilruth of Manned Spacecraft Center announced plans to develop a two-man Mercury capsule. Built by McDonnell, it would be similar in shape to the Mercury capsule but slightly larger and from two to three times heavier. Its booster would be a modified Titan II. A major program objective would be orbital rendezvous. The two-man spacecraft would be launched into orbit and would attempt to rendezvous with an Agena stage put into orbit by an Atlas. Total cost of 12 capsules plus boosters and other equipment was estimated at $500 million. The two-man flight program would begin in the 1963-1964 period with several unmanned ballistic flights to test overall booster-spacecraft compatibility and system engineering. Several manned orbital flights would follow. Besides rendezvous flybys of the target vehicle, actual docking missions would be attempted in final flights. The spacecraft would be capable of missions of a week or more to train pilots for future long-duration circumlunar and lunar landing flights. The Mercury astronauts would serve as pilots for the program, but additional crew members might be phased in during the latter portions of the program.

  • 1961 December 7 - Recommendations to Secretary of Defense Robert S. McNamara on the division of effort between NASA and DOD in the Mark II program. - Launch Vehicle: Atlas, Titan.
    NASA Associate Administrator Robert C. Seamans, Jr., and John H. Rubel, Department of Defense (DOD) Deputy Director for Defense Research and Engineering, offered recommendations to Secretary of Defense Robert S. McNamara on the division of effort between NASA and DOD in the Mark II program. They stressed NASA's primary responsibility for managing and directing the program, although attaining the program objectives would be facilitated by using DOD (especially Air Force) resources in a contractor relation to NASA. In addition, DOD personnel would aquire useful experience in manned spaceflight design, development, and operations. Space Systems Division of Air Force Systems Command became NASA's contractor for developing, procuring, and launching Titan II and Atlas-Agena vehicles for the Mark II program.

  • 1961 December 7 - Plans for Gemini announced - Program: Mercury.
    Plans for the development of a 2-man Mercury spacecraft were announced by Robert R. Gilruth, Director of the Manned Spacecraft Center. On January 3, 1962, this program was designated Project Gemini.

  • 1961 December 11 - NASA laid down guidelines for the development of the two-man spacecraft in a document included as Exhibit "A" in NASA's contract with McDonnell. -
    The development program had five specific objectives: (1) performing Earth-orbital flights lasting up to 14 days, (2) determining the ability of man to function in a space environment during extended missions, (3) demonstrating rendezvous and docking with a target vehicle in Earth orbit as an operational technique, (4) developing simplified countdown procedures and techniques for the rendezvous mission compatible with spacecraft launch vehicle and target vehicle performance, and (5) making controlled land landing the primary recovery mode. The two-man spacecraft would retain the general aerodynamic shape and basic systems concepts of the Mercury spacecraft but would also include several important changes: increased size to accommodate two astronauts; ejection seats instead of the escape tower; an adapter, containing special equipment not needed for reentry and landing, to be left in orbit; housing of most system hardware outside the pressurized compartment for ease of access; modular systems design rather than integrated; spacecraft systems for orbital maneuvering and docking; and a system for controlled land landing. Target date for completing the program was October 1965.

  • 1961 December 12 - Air Force / NASA working group to draft agreement on responsibilities in the Mercury Mark II program. -
    Colonel Daniel D. McKee of NASA Headquarters compiled instructions for an Air Force and NASA ad hoc working group established to draft an agreement on the respective responsibilities of the two organizations in the Mark II program. Manned Spacecraft Center (MSC) Director Robert R. Gilruth assigned his special assistant, Paul E. Purser, to head the MSC contingent.

  • 1961 December 15 - McDonnell given letter contract for Gemini - Program: Gemini.
    McDonnell given letter contract for development of Gemini.

  • 1961 December 22 - A week after receiving it, McDonnell accepted Letter Contract NAS 9-170 to "conduct a research and development program which will result in the development to completion of a Two-Man Spacecraft". -
    A week after receiving it, McDonnell accepted Letter Contract NAS 9-170 to 'conduct a research and development program which will result in the development to completion of a Two-Man Spacecraft.' McDonnell was to design and manufacture 12 spacecraft, 15 launch vehicle adapters, and 11 target vehicle docking adapters, along with static test articles and all ancillary hardware necessary to support spacecraft operations. Major items to be furnished by the Government to McDonnell to be integrated into the spacecraft were the paraglider, launch vehicle and facilities, astronaut pressure suits and survival equipment, and orbiting target vehicle. The first spacecraft, with launch vehicle adapter, was to be ready for delivery in 15 months, the remaining 11 to follow at 60-day intervals. Initial Government obligation under the contract was $25 million.

  • 1961 December 28 - Titan 2 first ground test. - Program: Gemini. Launch Vehicle: Titan.
    Titan II, an advanced ICBM and the booster designated for NASA's two-man orbital flights, was successfully captive-fired for the first time at the Martin Co.'s Denver facilities. The test not only tested the flight vehicle but the checkout and launch equipment intended for operational use.

  • 1961 December 29 - NASA issued the Gemini Operational and Management Plan, which outlined the roles and responsibilities of NASA and Department of Defense in the Gemini (Mercury Mark II) program. - Launch Vehicle: Atlas, Titan.
    NASA would be responsible for overall program planning, direction, systems engineering, and operation-including Gemini spacecraft development; Gemini/Agena rendezvous and docking equipment development; Titan II/Gemini spacecraft systems integration; launch, flight, and recovery operations; command, tracking, and telemetry during orbital operations; and reciprocal support of Department of Defense space projects and programs within the scope of the Gemini program. Department of Defense would be responsible for: Titan II development and procurement, Atlas procurement, Agena procurement, Atlas-Agena systems integration, launch of Titan II and Atlas-Agena vehicles, range support, and recovery support. A slightly revised version of the plan was signed in approval on March 27 by General Bernard A. Schriever, Commander, Air Force Systems Command, for the Air Force, and D. Brainerd Holmes, Director of Manned Space Flight, for NASA.

  • 1962 January 3 - "Gemini" became the official designation of the Mercury Mark II program. - Program: Gemini.
    The name had been suggested by Alex P. Nagy of NASA Headquarters because the twin stars Castor and Pollux in constellation Gemini (the Twins) seemed to him to symbolize the program's two-man crew, its rendezvous mission, and its relation to Mercury. Coincidentally, the astronomical symbol (II) for Gemini, the third constellation of the zodiac, corresponded neatly to the Mark II designation.

  • 1962 January 15 - James A. Chamberlin named Manager of Gemini Project Office (GPO). - Program: Gemini.
    Director Robert R. Gilruth of Manned Spacecraft Center (MSC) appointed James A. Chamberlin, Chief of Engineering Division, as Manager of Gemini Project Office (GPO). The next day MSC advised McDonnell, by amendment No. 1 to letter contract NAS 9-170, that GPO had been established. It was responsible for planning and directing all technical activities and all contractor activities within the scope of the contract.

  • 1962 January 23 - Manned Spacecraft Center completed an analysis of possible power sources for the Gemini spacecraft. Major competitors were fuel cells and solar cells. -
    Although any system selected would require much design, development, and testing effort, the fuel cell designed by General Electric Company, West Lynn, Massachusetts, appeared to offer decided advantages in simplicity, weight, and compatiblity with Gemini requirements over solar cells or other fuel cells. A basic feature of the General Electric design, and the source of its advantages over its competitors, was the use of ion-exchange membranes rather than gas-diffusion electrodes. On March 20, 1962, McDonnell let a $9 million subcontract to General Electric to design and develop fuel cells for the Gemini spacecraft.

  • 1962 January 31 - 11 Atlas-Agenas rendezvous targets requested for Project Gemini. -
    Manned Spacecraft Center notified Marshall Space Flight Center, Huntsville, Alabama (which was responsible for managing NASA's Agena Programs) that Project Gemini required 11 Atlas-Agenas as rendezvous targets and requested Marshall to procure them. The procurement request was accompanied by an Exhibit 'A' describing proposed Gemini rendezvous techniques and defining the purpose of Project Gemini as development and demonstrating Earth-orbit rendezvous techniques as early as possible. If feasible, these techniques could provide a practical base for lunar and other deep space missions. Exhibit B to the purchase request was a Statement of Work for Atlas-Agena vehicles to be used in Project Gemini. Air Force Space Systems Division, acting as a NASA contractor, would procure the 11 vehicles required. Among the modifications needed to change the Atlas-Agena into the Agena rendezvous vehicle were: incorporation of radar and visual navigation and tracking aids; main engines capable of multiple restarts; addition of a secondary propulsion system, stabilization system, and command system; incorporation of an external rendezvous docking unit; and provision of a jettisonable aerodynamic fairing to enclose the docking unit during launch. The first rendezvous vehicle was to be delivered to the launch site in 20 months, with the remaining 10 to follow at 60-day intervals.

  • 1962 February 13 - Technical aspects of earth orbit rendezvous meeting - Program: Apollo. Launch Vehicle: Saturn I, Saturn V.
    A meeting on the technical aspects of earth orbit rendezvous was held at NASA Headquarters. Representatives from various NASA offices attended: Arthur L. Rudolph, Paul J. DeFries, Fred L. Digesu, Ludie G. Richard, John W. Hardin, Jr., Ernst D. Geissler, and Wilson B. Schramm of Marshall Space Flight Center (MSFC); James T. Rose of MSC; Friedrich O. Vonbun, Joseph W. Siry, and James J. Donegan of Goddard Space Flight Center (GSFC); Douglas R. Lord, James E. O'Neill, Richard J. Hayes, Warren J. North, and Daniel D. McKee of the NASA Office of Manned Space Flight (OMSF). Joseph F. Shea, Deputy Director for Systems, OMSF, who had called the meeting, defined in general terms the goal of the meeting: to achieve agreement on the approach to be used in developing the earth orbit rendezvous technique. After two days of discussions and presentations, the Group approved conclusions and recommendations:

    • Gemini rendezvous operations could and must provide substantial experience with rendezvous techniques pertinent to Apollo.
    • Incorporation of the Saturn guidance equipment in a scaled-down docking module for the Agenas in the Gemini program was not required.
    • Complete development of the technique and equipment for Apollo rendezvous and docking should be required before the availability of the Saturn C-5 launch vehicle.
    • Full-scale docking equipment could profitably be developed by three- dimensional ground simulations. MSFC would prepare an outline of such a program.
    • The Apollo rendezvous technique and actual hardware could be flight- tested with the Saturn C-1 launch vehicle. MSFC would prepare a proposed flight test program.
    • The choice of connecting or tanking modes must be made in the near future. The MSFC Orbital Operations Study program should be used to provide data to make this decision.
    • The rendezvous technique which evolved from this meeting would place heavy requirements on the ground tracking network. GSFC should provide data relating the impact of detailed trajectory considerations to ground tracking station requirements.
    (This meeting was part of a continuing effort to select the lunar mission mode.)

  • 1962 February 19 - AiResearch received subcontract to manufacture the environmental control system (ECS) for Gemini. -
    AiResearch Manufacturing Company, a division of the Garrett Corporation, Los Angeles, California, received a $15 million subcontract from McDonnell to manufacture the environmental control system (ECS) for the Gemini spacecraft. This was McDonnell's first purchase order on behalf of the Gemini contract. Patterned after the ECS used in Project Mercury (also built by AiResearch), the Gemini ECS consisted of suit, cabin, and coolant circuits, and an oxygen supply, all designed to be manually controlled whenever possible during all phases of flight. Primary functions of the ECS were controlling suit and cabin atmosphere, controlling suit and equipment temperatures, and providing drinking water for the crew and storage or disposal of waste water.

  • 1962 February 22 - Proposal for redundant subsystems for the Gemini launch vehicle. - Launch Vehicle: Titan.
    Martin-Baltimore submitted its initial proposal for the redundant flight control and hydraulic subsystems for the Gemini launch vehicle; on March 1, Martin was authorized to proceed with study and design work. The major change in the flight control system from Titan II missile to Gemini launch vehicle was substitution of the General Electric Mod IIIG radio guidance system (RGS) and Titan I three-axis reference system for the Titan II inertial guidance system. Air Force Space Systems Division issued a letter contract to General Electric Company, Syracuse, New York, for the RGS on June 27. Technical liaison, computer programs, and ground-based computer operation and maintenance were contracted to Burroughs Corporation, Paoli, Pennsylvania, on July 3.

  • 1962 February 24 - McDonnell let a $32 million subcontract to North American Aviation's Rocktdyne Division, Sacramento, California, to build liquid propulsion systems for the Gemini spacecraft. -
    Two separate systems were required: the orbit attitude and maneuvering system (OAMS) and the reaction or reentry control system (RCS). The OAMS, located in the adapter section, had four functions: (1) providing the thrust required to enable the spacecraft to rendezvous with the target vehicle; (2) controlling the attitude of the spacecraft in orbit; (3) separating the spacecraft from the second stage of the launch vehicle and inserting it in orbit; and (4) providing abort capability at altitudes between 300,000 feet and orbital insertion. The OAMS initially comprised 16 ablative thrust chambers; eight 25-pound thrusters to control the spacecraft attitude in pitch, yaw, and roll axes; and eight 100-pound thrusters to maneuvre the spacecraft axially, vertically, and laterally. Rather than providing a redundant system, only critical components were to be duplicated. The RCS was located forward of the crew compartment in an independent RCS module. It consisted of two completely independent systems, each containing eight 25-pound thrusters very similar to those used in the OAMS. Purpose of the RCS was to maintain the attitude of the spacecraft during the reentry phase of the mission.

  • 1962 February 28 - Representatives of McDonnell, North American, Manned Spacecraft Center, and NASA Headquarters met to begin coordinating the interface between spacecraft and paraglider. -
    The first problem was to provide adequate usable stowage volume for the paraglider landing system within the spacecraft. The external geometry of the spacecraft had already been firmly established, so the problem narrowed to determining possible volumetric improvements within the spacecraft's recovery compartment.

  • 1962 March 5 - Harold I. Johnson, Head of the Spacecraft Operations Branch of Manned Spacecraft Center's Flight Crew Operations Division, circulated a memorandum on proposed training devices for Project Gemini. -
    A major part of crew training depended on several different kinds of trainers and simulators corresponding to various aspects of proposed Gemini missions. Overall training would be provided by the flight simulator, capable of simulating a complete mission profile including sight, sound, and vibration cues. Internally identical to the spacecraft, the flight simulator formed part of the mission simulator, a training complex for both flight crews and ground controllers that also included the mission control center and remote site displays. Training for launch and re-entry would be provided by the centrifuge at the Naval Air Development Center, Johnsville, Pennsylvania. A centrifuge gondola would be equipped with a mock-up of the Gemini spacecraft's interior. A static article spacecraft would serve as an egress trainer, providing flight crews with the opportunity to practice normal and emergency methods of leaving the spacecraft after landings on either land or water. To train flight crews in land landing, a boilerplate spacecraft equipped with a full-scale paraglider wing would be used in a flight program consisting of drops from a helicopter. A docking trainer, fitted with actual docking hardware and crew displays and capable of motion in six degrees of freedom, would train the flight crew in docking operations. Other trainers would simulate major spacecraft systems to provide training in specific flight tasks.

  • 1962 March 5 - Westinghouse Electric Corporation, Baltimore, Maryland, received a $6.8 million subcontract from McDonnell to provide the rendezvous radar and transponder system for the Gemini spacecraft. - Launch Vehicle: Atlas.
    Purpose of the rendezvous radar, sited in the recovery section of the spacecraft, was to locate and track the target vehicle during rendezvous maneuvers. The transponder, a combined receiver and transmitter designed to transmit signals automatically when triggered by an interrogating signal, was located in the Agena target vehicle.

  • 1962 March 7 - Subcontract to Honeywell to provide attitude control and maneuvering electronics system for Gemini. -
    McDonnell awarded a $6.5 million subcontract to Minneapolis-Honeywell Regulator Company, Minneapolis, Minnesota, to provide the attitude control and maneuvering electronics system for the Gemini spacecraft. This system commanded the spacecraft's propulsion systems, providing the circuitry which linked the astronaut's operation of his controls to the actual firing of thrusters in the orbit attitude and maneuvering system or the reaction control system.

  • 1962 March 8 - North American to develop an emergency parachute recovery system for flight test vehicles of the Paraglider Development Program. -
    Manned Spacecraft Center directed North American to design and develop an emergency parachute recovery system for both the half-scale and full-scale flight test vehicles required by Phase II-A of the Paraglider Development Program. They further authorized North American to subcontract the emergency recovery system to Northrop Corporation's Radioplane Division, Van Nuys, California. North American awarded the $225,000 subcontract to Radioplane on March 16. This was one of two major subcontracts led by North American for Phase II-A. The other, for $227,000, went to Goodyear to study materials and test fabrics for inflatable structures.

  • 1962 March 14 - Gemini seat ejection to be initiated manually. -
    Gemini Project Office (GPO) decided that seat ejection was to be initiated manually, with the proviso that the design must allow for the addition of automatic initiation if this should later become a requirement. Both seats had to eject simultaneously if either seat ejection system was energized. The ejection seat was to provide the crew a means of escaping from the Gemini spacecraft in an emergency while the launch vehicle was still on the launch pad, during the initial phase of powered flight (to about 60,000 feet), or in case of paraglider failure after reentry. In addition to the seat, the escape system included a hatch actuation system to open the hatches before ejection, a rocket catapult to propel the seat from the spacecraft, a personnel parachute system to sustain the astronaut after his separation from the seat, and survival equipment for the astronaut's use after landing. At a meeting on March 29, representatives of McDonnell, GPO, Life Systems Division, and Flight Crew Operations Division agreed that a group of specialists should get together periodically to monitor the development of the ejection seat, its related components, and the attendant testing. Although ejection seats had been widely used in military aircraft for years, Gemini requirements, notably for off-the-pad abort capability, were beyond the capabilities of existing flight-qualified systems. McDonnell awarded a $1.8 million subcontract to Weber Aircraft at Burbank, California, a division of Walter Kidde and Company, Inc, for the Gemini ejection seats on April 9; a $741,000 subcontract went to Rocker Power, Inc., Mesa, Arizona, on May 15 for the escape system rocket catapult.

  • 1962 March 17 - McDonnell awarded AiResearch a $5.5 million subcontract to provide the reactant supply system for the Gemini spacecraft fuel cells. -
    The oxygen and hydrogen required by the fuel cell were stored in two double-walled, vacuum-insulated, spherical containers located in the adapter section of the spacecraft. Reactants were maintained as single-phase fluids (neither gas nor liquid) in their containers by supercritical pressures at cryogenic temperatures. Heat exchangers converted them to gaseous form and supplied them to the fuel cells at operating temperatures.

  • 1962 March 19 - Thiokol Chemical Corporation, Elkton, Maryland, received a $400,000 sub-contract from McDonnell to provide the retrograde rockets for the Gemini spacecraft. -
    Only slight modification of a motor already in use was planned, and a modest qualification program was anticipated. Primary function of the solid-propellant retrorockets, four of which were located in the adapter section, was to decelerate the spacecraft at the start of the reentry maneuver. A secondary function was to accelerate the spacecraft to aid its separation from the launch vehicle in a high-altitude, suborbital abort.

  • 1962 March 19 - Advanced Technology Laboratories, Inc, Mountain View, California, received a $3.2 million subcontract from McDonnell to provide the horizon sensor system for the Gemini spacecraft. -
    Two horizon sensors, one primary and one standby, were part of the spacecraft's guidance and control system. They scanned, detected, and tracked the infrared radiation gradient between Earth and space (Earth's infrared horizon) to provide reference signals for aligning the inertial platform and error signals to the attitude control and maneuver electronics for controlling the spacecraft's attitude and its pitch and roll axes.

  • 1962 March 21 - McDonnell awarded a $4.475 million subcontract to the Western Military Division of Motorola, Inc, Scottsdale, Airzona, to design and build the digital command system (DCS) for the Gemini spacecraft. -
    Consisting of a receiver/decoder package and three relay packages, the DCS received digital commands transmitted from ground stations, decoded them and transferred them to the appropriate spacecraft systems. Commands were of two types: real-time commands to control various spacecraft functions and stored program commands to provide data updating the time reference system and the digital computer.

  • 1962 March 28 - McDonnell awarded a $2.5 million subcontract to Collins Radio Company, Cedar Rapids, Iowa, to provide the voice communications systems for the Gemini spacecraft. -
    Consisting of the voice control center on the center instrument panel of the spacecraft, two ultrahigh-frequency voice transceivers, and one high-frequency voice transceiver, this system provided communications between astronauts, between the blockhouse and the spacecraft during launch, between the spacecraft and ground stations from launch through reentry, and between the spacecraft and recovery forces after landing.

  • 1962 March 29 - The St. Petersburg, Florida, Aeronautical Division of Minneapolis-Honeywell received an $18 million subcontract from McDonnell to provide the inertial measuring unit (IMU) for the Gemini spacecraft. -
    The IMU was a stabilized inertial platform including an electronic unit and a power supply. Its primary functions were to provide a stable reference for determining spacecraft attitude and to indicate changes in spacecraft velocity.

  • 1962 March 31 - The configuration of the Gemini spacecraft was formally frozen. - Program: Gemini.
    Following receipt of the program go-ahead on December 22, 1961, McDonnell began defining the Gemini spacecraft. At that time, the basic configuration was already firm. During the three-month period, McDonnell wrote a series of detailed specifications to define the overall vehicle, its performance, and each of the major subsystems. These were submitted to NASA and approved. During the same period, the major subsystems specification control drawings - the specifications against which equipment was procured - were written, negotiated with NASA, and distributed to potential subcontractors for bid.

  • 1962 April 3 - Representatives of Manned Spacecraft Center, Ames Research Center, Martin, and McDonnell met to discuss the participation of Ames in the Gemini wind tunnel program. -
    The tests were designed to determine: (1) spacecraft and launch vehicle loads and the effect of the hatches on launch stability, using a six percent model of the spacecraft and launch vehicle; (2) the effect of large angles of attach, Reynold's number, and retrorocket jet effects on booster tumbling characteristics and attachment loads; (3) exit characteristics of the spacecraft; and (4) reentry characteristics of the reentry module.

  • 1962 April 7 - ACF Electronics Division, Riverdale, California, of ACF Industries, Inc., received a $1 million subcontract from McDonnell to provide C- and S-band radar beacons for the Gemini spacecraft. -
    These beacons formed part of the spacecraft's tracking system. With the exception of frequency-dependent differences, the C-band beacon was nearly identical to the S-band beacon. Their function was to provide tracking responses to interrogation signals from ground stations.

  • 1962 April 18 - NASA announced that applications would be accepted for additional astronauts until June 1, 1962. -
    NASA planned to select five to ten astronauts to augment the seven-member Mercury astronaut team. The new pilots would participate in support operations in Project Mercury and would join the Mercury astronauts in piloting the two-man Gemini spacecraft. To be chosen, the applicant must (1) be an experienced jet test pilot and preferably be presently engaged in flying high-performance aircraft; (2) have attained experimental flight test status through military service, aircraft industry, or NASA, or must have graduated from a military test pilot school; (3) have earned a degree in the physical or biological sciences or in engineering; (4) be a United States citizen under 35 years of age at the time of selection, six feet or less in height; and (5) be recommended by his parent organization. Pilots meeting these qualifications would be interviewed in July and given written examinations on their engineering and scientific knowledge. Selected applicants would then be thoroughly examined by a group of medical specialists. The training program for the new astronauts would include work with design and development engineers, simulator flying, centrifuge training, additional scientific training, and flights in high-performance aircraft.

  • 1962 April 19 - McDonnell awarded a $26.6 million subcontract to International Business Machines (IBM) Corporation's Space Guidance Center, Owego, New York, to provide the computer system for the Gemini spacecraft. -
    The digital computer was the heart of the spacecraft's guidance and control system; supplementary equipment consisted of the incremental velocity indicator (which visually displayed changes in spacecraft velocity), the manual data insertion unit (for inserting data into, and displaying readouts from, the computer), and the auxiliary computer power unit (to maintain stable computer input voltages). In addition to providing the computer and its associated equipment, IBM was also responsible for integrating the computer with the systems and components it connected with electrically, including the inertial platform, rendezvous radar, time reference system, digital command system, data acquisition system, attitude control and maneuver electronics, the launch vehicle autopilot, console controls and displays, and aerospace ground equipment.

  • 1962 April 25 - Studebaker subcontract for two backup heatshields for the Gemini spacecraft. -
    Studebaker Corporation's CTL Division, Cincinnati, Ohio, received a subcontract for $457,875 from McDonnell to provide two backup heatshields for the Gemini spacecraft, similar in material and fabrication technique to those used in Project Mercury. The CTL heatshield would be used only if a new shield McDonnell was working on proved unusable. Test results from screening advanced heatshield materials had yielded four promising materials. McDonnell had contracted with Vidya, Inc., Palo Alto, California (March 16), and Chicago Midway Laboratories, Chicago, Illinois (mid-April), to test the new ablation materials.

  • 1962 April 26 - Meeting to review the design and testing philosophy for the half-scale test vehicle (HSTV) in phase II-A. -
    Representatives of North American, NASA Headquarters, Langley Research Center, Flight Research Center, Ames Research Center, and Manned Spacecraft Center met to review the design and testing philosophy for the half-scale test vehicle (HSTV) in phase II-A of the Paraglider Development Program. After the emergency parachute recovery system had been qualified, the HSTV would be used to evaluate paraglider stability and control in drop tests with the wing predeployed and to provide empirical data on the functioning of vehicle systems in deployment tests. At the end of the review, the NASA Half Scale Test Vehicle Design Review Board recommended 21 changes in test vehicle design and test procedures to North American.

  • 1962 May 1 - McDonnell proposed to evaluate the Gemini redezvous radar and spacecraft maneuvering system on early flights by using a rendezvous evaluation pod to be ejected from the spacecraft in orbit. -
    Manned Spacecraft Center (MSC) liked the idea and asked McDonnell to pursue the study. During the last week in June, McDonnell received approval from MSC to go ahead with the design and development of the rendezvous pod. It would contain a radar transponder, C-band beacon, flashing light, and batteries.

  • 1962 May 10 - The postlanding survival kit proposed for use by Gemini crew members would be basically similar to the one used in Project Mercury. -
    Each kit would weigh about 24 pounds, and one kit would be provided for each crew member.

  • 1962 May 12 - Project Gemini cost estimates had tripled from the original estimate of $250 million. - Program: Gemini. Launch Vehicle: Atlas, Titan.
    James E. Webb, NASA's new Administrator, reviewed the Gemini program. Project Gemini cost estimates at this point ($744.3 million) had increased substantially over the original estimate of $250 million. Estimated spacecraft cost had risen from $240.5 to $391.6 million; Titan II cost, from $113.0 to $161.8 million; Atlas-Agena, from $88.0 to $106.3 million; and supporting development (including the paraglider program), from $29.0 to $36.8 million. Estimated operations costs had declined from $59.0 to $47.8 million.

  • 1962 May 14 - Representatives of McDonnell, Northrop Ventura (formerly Radioplane), Weber Aircraft, and Manned Spacecraft Center attended the first ejection seat design review at McDonnell in St Louis. -

  • 1962 May 16 - At a mechanical systems coordination meeting, representatives of McDonnell and Gemini Project Office decided to develop more powerful retrograde rocket motors for the Gemini spacecraft. -
    The new motors, similar in configuration to the old but with some three times the thrust level, would permit retrorocket aborts at altitudes as low as 72,000 to 75,000 feet. McDonnell's original subcontract with Thiokol was accordingly terminated and a new subcontract was let on July 20. Development of the new motors was expected to cost $1.255 million.

  • 1962 May 18 - McDonnell subcontracted the parachute landing system for Gemini to Northrop Ventura at an estimated cost of $1,829,272. -
    The parachute landing system was to be used for the first Gemini flight. Gemini Project Office had decided in April on using a single-chute system, one 84.2-foot diameter ring-sail parachute. At a mechanical systems coordination meeting in Houston on May 16-17, however, it was decided to add an 18-foot ring-sail drogue parachute to the system. McDonnell proposed deploying the drogue at 10,000 feet, two seconds after release of the rendezvous and recovery system. Fifteen seconds later the main recovery parachute would switch from single-point to two-point suspension, followed in five seconds by the initiation of reaction control system propellant dump which would take no longer that 105 seconds. The recovery parachute would be jettisoned shortly after impact. At another coordination meeting on May 23-24, Manned Spacecraft Center concurred in this proposed sequencing.

  • 1962 May 23 - Manned Spacecraft Center concurred in McDonnell's proposed sequencing of the paraglider recovery system. -
    In a normal mission, the drogue parachute (a small parachute to pull the recovery compartment away from the spacecraft and strip the paraglider from the recovery compartment) would deploy at 60,000 feet, followed by the release of the rendezvous and recovery section at 50,000 feet. Starting at 10,000 feet, all reaction control system propellant remaining after the paraglider had been deployed would be dumped. The paraglider wing itself would be jettisoned shortly after touchdown. At this point, plans called for the paraglider to be used on all Gemini missions except the first.

  • 1962 May 23 - Ames Research Center began the first wind tunnel test of the half-scale inflatable paraglider wing in support of the Paraglider Development Program. -
    This was the first test of a large-scale inflatable paraglider wing in the full-scale test facility. Purpose of the test was to obtain basic aerodynamic and loads data for the combined wing/spacecraft system and to spot and evaluate potential aerodynamic and design problem areas. The flight regimes studied included wing deployment as well as glide, preflare, and flare. In the last stages of the test, the sail ripped. Since the basic objectives had already been achieved, and the failure occurred under conditions more stringent than any expected during flight testing, only minor corrective action was considered necessary and the test was not repeated. Testing ended July 25; at a paraglider landing system coordination meeting on July 26, the Ames test program was considered completed.

  • 1962 May 24 - North American began a test program to qualify the emergency parachute system for the half-scale flight test vehicle required for Phase II-A of the Paraglider Development Program. -
    The first two drop tests were successful (May 24, June 20); but during the third (July 10), the main recovery parachute failed to deploy. The trouble was analyzed and detailed modifications were worked out at a meeting on August 16 between North American and Northrop Ventura. The modifications proved successful in the fourth test (September 4), and Manned Spacecraft Center concurred with North American in judging the emergency parachute system for the half-scale test program to be qualified.

  • 1962 May 29 - Plans for development testing of the Gemini ejection seat. -
    Representatives of McDonnell, Weber Aircraft, Gemini Procurement Office, Life Systems Division, Gemini Project Office, and US Naval Ordnance Test Station, China Lake, California, concluded plans for development testing of the spacecraft ejection seat. Requirements peculiar to the Gemini spacecraft, in particular off-the-pad abort capability, caused the plan to stress testing from a stationary tower early in the test program. The purpose of these simulated off-the-pad ejection tests was to investigate the effects of varying the center of gravity on the trajectory of the ejected seat and to optimize the timing of the recovery sequence. Tower tests began July 2. They were to be followed by rocket sled ejection tests to investigate simultaneous ejection with open hatches at maximum dynamic pressure. Sled tests actually began on November 9, before tower tests had been completed.

  • 1962 June 4 - The Air Force School of Aviation Medicine, Brooks Air Force Base, Texas, began a simulated long-duration Gemini mission. -
    Two men were to live for 14 days in a 100-percent-oxygen atmosphere maintained at a pressure of 5 pounds per square inch, the proposed spacecraft environment.

  • 1962 June 6 - McDonnell was authorized to procure an additional boilerplate spacecraft for parachute landing system tests. -
    The original plan called for McDonnell to use the boilerplate spacecraft fabricated by North American for qualification testing of the emergency parachute system for the paraglider drop tests. McDonnell estimated, however, that modifying the North American boilerplate would cost from $17,000, to $19,000, whereas a new boilerplate would cost from $10,000 to $12.000.

  • 1962 June 20 - Manned Spacecraft Center authorized North American to go ahead with Phase II, Part B(1), of the Paraglider Development Program. -
    Letter contract NAS 9-539 followed. Under this contract, North American was to design, build and test an advanced two-man paraglider trainer, to initiate a flight simulation program for pilot training, and to complete the design of a man-rated Gemini paraglider wing. The final contract was awarded on October 31, 1962.

  • 1962 June 21 - A paraglider full-scale test vehicle Design Engineering Inspection was held at North American's Space and Information Systems Division in Downey, California. -
    The Manned Spacecraft Center inspecting team reviewed the design of the full-scale paraglider wing, capsule, and associated equipment, as well as the test program and schedules for Phase II-A of the Paraglider Development Program. The team suggested 33 changes, mostly related to hardware.

  • 1962 June 25 - Gemini Project Office reported that a thorough study of the reentry tracking histories of the Mercury-Atlas 4, 5, 6 and 7 missions had been completed. -
    The study indicated that a C-band radar tracking beacon should be integrated into the spacecraft reentry section in place of the planned S-band beacon. The change would improve the probability of tracking spacecraft reentry through the ionization zone.

  • 1962 June 28 - McDonnell and North American representatives met for the first time to exchange detailed technical information on the installation of the paraglider in the spacecraft. -

  • 1962 July 2 - Simulated off-the-pad ejection tests began at Naval Ordnance Test Station. -
    Five ejections were completed by the first week of August. The tests revealed difficulties which led to two important design changes: the incorporation of a drogue-gun method of deploying the personnel parachute and the installation of a three-point restraint-harness-release system similar to those used in military aircraft. August 6-7 representatives of Manned Spacecraft Center and ejection system contractors met to review the status of ejection seat design and the development test program. They decided that off-the-pad ejection tests would not be resumed until ejection seat hardware reflected all major anticipated design features and the personnel parachute had been fully tested. Design changes were checked out in a series of bench and ground firings, concluding on August 30 with a successful inflight drop test of a seat and dummy. Off-the-pad testing resumed in September.

  • 1962 July 11 - The capability for successfully accomplishing water landings with either the parachute landing system or the paraglider landing system was established as a firm requirement for the Gemini spacecraft. -
    The spacecraft would be required to provide for the safety of the crew and to be seaworthy during a water landing and a 36-hour postlanding period.

  • 1962 July 19 - Gemini Project Office and North American agreed on guidelines for the design of the advanced paraglider trainer, the paraglider system to be used with static test article No. -
    2, and the paraglider system for the Gemini spacecraft. The most important of these guidelines was that redundancy would be provided for all critical operations.

  • 1962 July 20 - NASA Mission Control Center would be located at Houston - Program: Apollo.
    NASA Administrator James E. Webb announced that the Mission Control Center for future manned space flights would be located at MSC. The Center would be operational in time for Gemini rendezvous flights in 1964 and later Apollo lunar missions. The overriding factor in the choice of MSC was the existing location of the Apollo Spacecraft Project Office, the astronauts, and Flight Operations Division at Houston.

  • 1962 July 25 - McDonnell reported reducing the rated thrust of the two forward-firing thrusters from 100 pounds to 85 pounds to reduce disturbance torques generated in the event of maneuvers with one engine out. -

  • 1962 July 29 - Adaptation of the Gemini-type heatshield to Apollo - Program: Apollo.
    As a result of an MSC in-house technical review, NAA was directed to investigate the adaptation of the Gemini-type heatshield to the Apollo spacecraft.

  • 1962 August 1 - Rocketdyne completed designing and fabricating prototype hardware for both spacecraft liquid propulsion systems and initiated testing of the reaction control system. -
    Test firing of the 25-pound-thrust chambers revealed nozzle erosion causing degradation in performance after one third the specified burn time.

  • 1962 August 2 - North American began a test program to qualify the emergency parachute recovery system for the full-scale test vehicle in Phase II-A of the Paraglider Development Program. -
    The first test was successful. In the second test (August 22), one of the three main parachutes was lost after deployment, but no damage resulted. In the third test (September 7), only minor damage was sustained despite the loss of two parachutes. The test series ended on November 15 when all recovery parachutes separated from the spacecraft immediately after deployment and the test vehicle was destroyed on impact. Manned Spacecraft Center decided to terminate this portion of the test program but directed McDonnell to supply North American with a boilerplate spacecraft for further tests at a later date.

  • 1962 August 8 - Facilities at El Centro Apollo and Gemini drop-tests - Program: Apollo.
    Representatives of the MSC Gemini Project Office and Facilities Division inspected the proposed hangar and office facilities to be refurbished at El Centro Naval Air Facility, Calif., for joint use in the Apollo and Gemini drop-test programs.

  • 1962 August 14 - Flight tests of the half-scale vehicle (HSTV) in the Paraglider Development Program. - Program: Gemini.
    North American began flight tests of the half-scale vehicle (HSTV) in Phase II-A of the Paraglider Development Program two months behind schedule. The instrumented HSTV with the paraglider predeployed was towed aloft by helicopter. Objectives of the predeployed flights were to evaluate flight performance, longitudinal and lateral control characteristics, effectiveness of control, and the flare maneuver capability of the paraglider. Despite various minor malfunctions in all five test flights (August 14, 17, 23, September 17, and October 23, 1962), test results verified the stability of the wing/vehicle combination in free flight and the adequacy of control effectiveness.

  • 1962 August 15 - Manned Spacecraft Center reviewed engineering mock-up of the Gemini spacecraft. - Program: Gemini.
    Manned Spacecraft Center (MSC) formally reviewed McDonnell's engineering mock-up of the Gemini spacecraft in St Louis. The company had begun building the mock-up in January, shortly after receiving the spacecraft contract. Mock-up review had originally been scheduled for mid-July, but informal examinations by MSC representatives, including James A Chamberlin and several astronauts, had produced some suggested changes. The review itself resulted in McDonnell's receiving 167 requests for alterations. MSC inspected the revised mock-up in November.

  • 1962 September 1 - George W. Jeffs became Program Manager of the Paraglider Development Program at North American. -
    He replaced N. F. Witte, who remained as Assistant Program Manager. This organizational change reflected the elevation of work on paraglider from project to program status within North American's Space and Information Systems Division. The paraglider program achieved operating division status three months later when Jeffs was appointed Vice President of Space and Information Systems Division.

  • 1962 September 4 - Gemini Project Office directed McDonnell to provide spacecraft No. 3 with rendezvous radar capability and to provide a rendezvous evaluation pod as a requirement for missions 2 and 3. - Flight: Gemini 3.
    Four pods were required: one prototype, two flight articles, and one flight spare.

  • 1962 September 6 - A study group formed at the Gemini mock-up review of August 15-16 met to review the ejection seat development program. -
    McDonnell reported the successful completion of redesign and testing which cleared the way for resumption of off-the-pad developmental testing. McDonnell described the major outstanding design task as the determination of the dynamic center of gravity of the seat-man combination under expected acceleration profiles.

  • 1962 September 12 - Simulated off-the-pad tests of the redesigned Gemini escape system resumed with test No. 6. Test No. -
    7 followed on September 20. Though primarily successful, these tests revealed some problems. The seat-structure thrust pad required reanalysis and redesign. Simulated off-the-pad testing was temporarily halted until a final configuration rocket catapult became available. A rocket motor test on January 4, 1963, demonstrated the structural integrity of the thrust-pad area, and simulated pad ejection tests resumed the following month.

  • 1962 September 17 - Nine new astronauts named - Program: Gemini.
    NASA's nine new astronauts were named in Houston, Tex., by Robert R. Gilruth, MSC Director. Chosen from 253 applicants, the former test pilots who would join the original seven Mercury astronauts in training for Projects Gemini and Apollo were: Neil A. Armstrong, NASA civilian test pilot; Maj. Frank Borman, Air Force; Lt. Charles Conrad, Jr., Navy; Lt.Cdr. James A, Lovell, Jr., Navy; Capt. James A. McDivitt, Air Force; Elliot M. See, Jr., civilian test pilot for the General Electric Company; Capt. Thomas P. Stafford, Air Force; Capt. Edward H. White II, Air Force; and Lt. Cdr. John W. Young, Navy.

  • 1962 September 19 - ACF Electronics delivered an engineering prototype radar beacon to McDonnell. -
    An engineering prototype C-band beacon had operated at ACF Electronics under simulated reentry conditions with no degredation in performance.

  • 1962 September 30 - Freeze-dried food for the Apollo program - Program: Apollo.
    The freeze-dried food that would be used in the Gemini program would also be provided for the Apollo program. Forty-two pounds of food would be necessary for a 14-day lunar landing mission. Potable water would be supplied by the fuel cells and processed by the environmental control system. A one-day water supply of six pounds per man would be provided at launch as an emergency ration if needed before the fuel cells were fully operative.

  • 1962 October 5 - Radiation hazards for Gemini missions. - Program: Gemini.
    McDonnell and Lockheed reported on radiation hazards and constraints for Gemini missions at a Trajectories and Orbits Coordination meeting. McDonnell's preliminary findings indicated no radiation hazard for normal Gemini operations with some shielding; with no shielding the only constraint was on the 14-day mission, which would have to be limited to an altitude of 115 nautical miles. Lockheed warned that solar flares would pose a problem at higher altitudes. Lockheed also recommended limiting operations to under 300 miles pending more data on the new radiation belts created by the Atomic Energy Commission's Project Dominic in July 1962.

  • 1962 October 16 - Selection of the IBM to provide ground-based computer system for Projects Gemini and Apollo - Program: Apollo.
    NASA announced the selection of the International Business Machines Corporation to provide a ground-based computer system for Projects Gemini and Apollo. The computer complex would be part of the mission control center at MSC.

  • 1962 October 19 - NASA Headquarters' recent decision to cut the MSC budget for fiscal year 1963 from $687 million to $660 million. - Launch Vehicle: Atlas.
    Wesley L. Hjornevik, Manned Spacecraft Center (MSC) Assistant Director for Administration, described to members of MSC's senior staff the implications of NASA Headquarters' recent decision to cut the MSC budget for fiscal year 1963 from $687 million to $660 million, the entire reduction to be borne by the Gemini program. Hjornevik feared that the Gemini budget, already tight, could absorb so large a cut only by dropping the paraglider, Agena, and all rendezvous equipment from the program. Gemini Project Office (GPO) reported that funding limitations had already forced Martin and McDonnell to reduce their level of activity. The first Gemini flight (unmanned) was rescheduled for December 1963, with the second (manned) to follow three months later, and subsequent flights at two-month intervals, with the first Agena (fifth mission) in August or September 1964. This four-month delay imposed by budget limitations required a large-scale reprogramming of Gemini development work, reflected chiefly in drastic reduction in the scale of planned test programs. Details of the necessary reprogramming had been worked out by December 20, when GPO Manager James A. Chamberlin reported that December 1963 was a realistic date for the first Gemini flight. Gemini funding for fiscal year 1963 totaled $232.8 million.

  • 1962 October 23 - Gemini ground support equipment for Apollo program - Program: Apollo.
    At the request of NASA, about 300 pieces of Gemini ground support equipment were examined by NAA engineers. It appeared that about 190 items would be usable on the Apollo program.

  • 1962 October 31 - Gemini fuel cell for the lunar excursion module studied - Program: Apollo.
    The feasibility of using the Gemini fuel cell for the lunar excursion module was studied by NAA. However, because of modifications to meet Apollo control and auxiliary requirements, the much lighter Gemini system would ultimately weigh about as much as the Apollo fuel cell. In addition, the Gemini fuel cell schedule would slip if the system had to be adapted to the Apollo mission.

  • 1962 October 31 - The apogee of the basic spacecraft orbit model was set at 167 nautical miles, the perigee of the elliptical orbit at 87. -
    The altitude of the circular orbit of the target vehicle was to be 161 nautical miles.

  • 1962 November 9 - Sled ejection test No. 1 was conducted at Naval Ordnance Test Station. -
    Despite its designation, this test did not call for seats actually to be ejected. Its purpose was to provide data on the aerodynamic drag of the test vehicle and to prove the test vehicle's structural soundness in preparation for future escape system tests. The test vehicle, mounted by boilerplate spacecraft No. 3 (a welded steel mock-up of the Gemini spacecraft aerodynamically similar to the flight article), was a rocket-propelled sled running on tracks. Although test objectives were achieved, the boilerplate spacecraft was severly damaged when one of the sled motors broke loose and penetrated the heatshield, causing a fire which destroyed much instrumentation and equipment. Despite repairs required for the boilerplate and major modification or rebuilding of the sled, Gemini Project Office foresaw no delay in the sled test program.

  • 1962 November 20 - Invitations to ten firms to submit bids for a manned spaceflight control center at Houston - Program: Apollo.
    NASA invited ten industrial firms to submit bids by December 7 for a contract to build a control center at MSC and to integrate ground operational support systems for Apollo and the rendezvous phases of Gemini. On January 28, 1963, NASA announced that the contract had been awarded to the Philco Corporation, a subsidiary of the Ford Motor Company.

  • 1962 November 21 - McDonnell's subcontract with Studebaker for the backup heatshield terminated. -
    At a mechanical systems coordination meeting, representatives of McDonnell and Manned Spacecraft Center decided to terminate McDonnell's subcontract with CTL Division of Studebaker for the backup heatshield. The decision resulted from growing confidence in the new McDonnell design as well as from CTL problems in fabricating heatshield No. 1. Termination of the CTL contract would save an estimated $131,000.

  • 1962 November 30 - Gemini primary problem area the 25-pound thruster. -
    Gemini Project Office identified the primary problem area of the spacecraft liquid propellant rocket systems to be the development of a 25-pound thruster able to perform within specification over a burn time of five minutes. Three-minute chambers for the reaction control system (RCS) had been successfully tested, but the longer-duration chambers required for the orbit attitude and maneuver system (OAMS) had not. Rocketdyne was three weeks behind schedule in developmental testing of RCS and OAMS components, and five weeks behind in the systems testing.

  • 1962 December 10 - North American began deployment flight testing of the half-scale test vehicle (HSTV) in Phase II-A of the Paraglider Development Program. -
    The HSTV was carried aloft slung beneath a helicopter. The main purpose of the deployment flight tests was to investigate problem areas in the transition from release of the rendezvous and recovery canister to glide - the ejection, inflation, and deployment of the paraglider wing. The first flight partially substantiated the feasibility of the basic deployment sequence, but emergency recovery procedures were necessary. In the second test (January 8, 1963), the sail disintegrated, and in the third (March 11), the rendezvous and recovery canister failed to separate. In both instances, attempts to recover the vehicle with the emergency system were thwarted when the main parachute failed to deploy, and both vehicles were destroyed on impact.

  • 1962 December 10 - Design Engineering Inspection of the full-scale test vehicle (FSTV) for Phase II-A of the Paraglider Development Program. -
    Representatives of Manned Spacecraft Center, NASA Headquarters, Flight Research Center, Langley Research Center, and Ames Research Center conducted a Design Engineering Inspection of the full-scale test vehicle (FSTV) for Phase II-A of the Paraglider Development Program. As conceived during Phase I of the program, the FSTVs (the contract called for two) were to be a means of meeting a twofold objective: (1) the development of systems and techniques for wing deployment and (2) the evaluation of flight performance and control characteristics during glide. After reviewing flight test objectives, test vehicle hardware, and electrical and electronic systems, the inspecting team submitted 24 requests for alterations to North American.

  • 1962 December 14 - A 10-percent fluctuating-pressure model of the Gemini spacecraft completed its exit configuration test program in the mach number range of 0.6 to 2.5, the region of maximum dynamic pressure. -
    On January 15, 1963, a Gemini spacecraft dynamics stability model also completed its test program providing dynamic stability coefficients for the spacecraft reentry at mach numbers 3.0 to 10. These tests completed all the originally scheduled wind tunnel testing for Project Gemini; however, three additional test programs had been initiated. These included additional testing of the spacecraft 20-percent ejection seat model, testing of the astronaut ballute model to obtain data for design of the astronaut stabilization system, and testing of the rigid frame paraglider model to determine optimum sail configuration.

  • 1963 January 4 - Manned Spacecraft Center directed McDonnell to study requirements for a spacecraft capable of performing rendezvous experiments on the second and third Gemini flights. -
    The experimental package would weigh 70 pounds and would include an L-band radar target, flashing light, battery power supply, and antenna systems. On the second flight, a one-day mission, the experiment was to be performed open-loop, probably optically - the astronaut would observe the target and maneuver the spacecraft to rendezvous with it. On the third flight, a seven-day mission, the experiment was to be performed closed-loop, with spacecraft maneuvers controlled automatically by the data it received from its instruments.

  • 1963 January 8 - Manned Spacecraft Center outlined requirements for McDonnell to consider concerning aborts in orbit. -
    These included onboard controlled reentry for all aborts, except in the event of guidance and control system failure; onboard selection of one of the emergency abort target areas; navigational accuracy to a two-mile radius error at the point of impact; and crew capability to eject from the spacecraft with the paraglider deployed.

  • 1963 January 8 - Design Engineering Inspection of the advanced trainer for the Paraglider Development Program, Phase II-B. -
    Representatives of Manned Spacecraft Center, NASA Headquarters, Flight Research Center, Langley Research Center, and Ames Research Center conducted a Design Engineering Inspection of the advanced trainer for the Paraglider Development Program, Phase II-B(1). North American received 36 requests for alterations.

  • 1963 January 11 - Astronauts to visit with workers at various contractors' plants. -
    To stimulate contractor employees to better performance, Gemini Project Office Manager James A. Chamberlin suggested that astronauts visit with workers at various contractors' plants. Donald K Slayton, Astronaut Activities Office, informed Chamberlin that such visits would be made, beginning with the Martin Company in February 1963.

  • 1963 January 14 - Gemini on-board computer issues. -
    In the opinion of Flight Operations Division's Project Gemini working group: 'One of the biggest problem areas seems to be the on-board computer; exactly what is it going to do; what is its sequence of operation; what does it need from the ground computer complex and how often; exactly how is it used by astronauts; what is the job of the on-board computer for early missions?'

  • 1963 January 19 - McNamara requests review of the Titan III nd Gemini programs. - Launch Vehicle: Titan.
    The Secretary of Defense directed a review of the Titan III program and the Gemini program of NASA.

  • 1963 January 21 - Defense department participation in Gemini program. -
    The Department of Defense and the National Aeronautics and Space Administration completed an agreement for defense department participation in the Gemini program.

  • 1963 January 22 - Results of operating the first fuel cell section. -
    In an electrical systems coordination meeting at Manned Spacecraft Center, results of operating the first fuel cell section were reported: a fuel cell stack had failed and the resultant fire had burned a hole through the case. Another section was being assembled from stacks incorporating thicker ion-exchange membranes. One such stack, of six fuel cells, had operated for 707 hours within specification limits, and after 875 hours was five percent below specified voltage; a similar stack was well within specification after operating 435 hours.

  • 1963 January 22 - North American received a letter contract for Phase III, Part I, of the Paraglider Development Program, to produce a Gemini paraglider landing system. -
    This contract was subsequently incorporated as Change No. 6 to Contract NAS 9-539, Phase II-B(1) of the Paraglider Development Program.

  • 1963 January 26 - New assignments for the seven original astronauts - Program: Apollo.
    MSC announced new assignments for the seven original astronauts: L. Gordon Cooper, Jr., and Alan B. Shepard, Jr., would be responsible for the remaining pilot phases of Project Mercury; Virgil I. Grissom would specialize in Project Gemini; John H. Glenn, Jr., would concentrate on Project Apollo; M. Scott Carpenter would cover lunar excursion training; and Walter M. Schirra, Jr., would be responsible for Gemini and Apollo operations and training. As Coordinator for Astronaut Activities, Donald K. Slayton would maintain overall supervision of astronaut duties.

    Specialty areas for the second generation were: trainers and simulators, Neil A. Armstrong; boosters, Frank Borman; cockpit layout and systems integration, Charles Conrad, Jr.; recovery system, James A. Lovell, Jr.; guidance and navigation, James A. McDivitt; electrical, sequential, and mission planning, Elliot M. See, Jr.; communications, instrumentation, and range integration, Thomas P. Stafford; flight control systems, Edward H. White II; and environmental control systems, personal equipment, and survival equipment, John W. Young.

  • 1963 January 26 - Manned Spacecraft Center announced specialty areas for the nine new astronauts. -
    Manned Spacecraft Center announced specialty areas for the nine new astronauts: trainers and simulators, Neil A. Armstrong; boosters, Frank Borman; cockpit layout and systems integration, Charles Conrad, Jr.; recovery systems, James A. Lovell, Jr.; guidance and navigation, James A. McDivitt; electrical, Sequential, and mission planning, Elliot M. See, Jr.; communications, instrumentation, and range integration, Thomas P. Stafford; flight control systems, Edward H White II; and environmental control systems, personal and survival equipment, John W Young.

  • 1963 February 1 - Location of earth landing sites for Gemini and Apollo - Program: Apollo.
    Walter C. Williams, MSC's Associate Director, defined the Center's criteria on the location of earth landing sites for Gemini and Apollo spacecraft: site selection as well as mode of landing (i.e., land versus water) for each mission should be considered separately. Constraints on trajectory, landing accuracy, and landing systems must be considered, as well as lead time needed to construct landing area facilities. Both Gemini and Apollo flight planning had to include water as well as land landing modes.Although the Apollo earth landing system was designed to withstand the shock of coming down on varying terrains, some experience was necessary to verify this capability. Because of the complexity of the Apollo mission and because the earth landing system did not provide a means of avoiding obstacles, landing accuracy was even more significant for Apollo than for Gemini. With so many variables involved, Williams recommended that specific landing locations for future missions not be immediately designated.

  • 1963 February 6 - Astronaut trainees concluded their formal academic training with a course on orbital mechanics and flight dynamics. -
    Flight crew personnel had been receiving basic science training for two days a week over the past four months. During this period, they also received Gemini spacecraft and launch vehicle familiarization courses and visited several contractor facilities, including McDonnell, Martin, Aerojet, and Lockheed. Among subjects studied were astronomy, physics of the upper atmosphere and space, global meteorology, selenology, guidance and navigation, computers, fluid mechanics, rocket propulsion systems, aerodynamics, communications, environmental control systems, and medical aspects of space flight. Flight-crew training plans for the rest of the year, which were being formulated during February, called for space science and technology seminars, celestial recognition training, monitoring the Mercury-Atlas 9 flight, weightless flying, pressure suit indoctrination, parachute jumping, survival training, instruction in spacecraft systems and launch support, paraglider flying, centrifuge experience, docking practice, and work with the flight simulator.

  • 1963 February 7 - Simulated off-the-pad ejection test No. 8. - Program: Gemini.
    Simulated off-the-pad ejection test No. 8 was conducted at Naval Ordnance Test Station. Two dummies were ejected, and for the first time the test incorporated a ballute system. The ballute (for balloon + parachute) had been introduced as a device to stabilize the astronaut after ejection at high altitudes. Ejection seat and dummy separated satisfactorily and the personnel parachute deployed properly; but faults in the test equipment prevented the canopy from fully inflating. The ballute failed to inflate or release properly on either dummy. As a result, the parachute was redesigned to ensure more positive inflation at very low dynamic pressures. The redesigned chute was tested in a series of five entirely successful dummy drops during March.

  • 1963 February 8 - Department of Defense objectives in the Gemini program. - Program: Gemini.
    Colonel Kenneth W Schultz of Headquarters, Air Force Office of Development Planning, outlined Department of Defense objectives in the Gemini program at the first meeting of the Gemini Program Planning Board. He defined three general objectives: conducting orbital experiments related to such possible future missions as the inspection and interception of both cooperative and passive or noncooperative objects in space under a variety of conditions, logistic support of a manned orbiting laboratory, and photo reconnaissance from orbit; gaining military experience and training in all aspects of manned space flight; and assessing the relationship between man and machine in the areas of potential military missions.

  • 1963 February 15 - Agena target vehicle checkout plans were presented at a meeting of the Gemini Management Panel. - Launch Vehicle: Atlas.
    Upon receipt at Cape Canaveral, the target vehicle would be inspected and certified. After this action, mechanical mate and interface checks with the target docking adapter would be accomplished. Agena-Gemini spacecraft compatibilty tests would then be conducted, and the Agena would undergo validation and weight checks. Subsequently, a joint checkout of the spacecraft and Agena would be conducted with tests on the Merritt Island radar tower.

  • 1963 February 28 - Gemini Project Office (GPO) published a bar chart depicting preflight check-out of the Gemini spacecraft in the industrial area at Cape Canaveral. -
    The chart outlined tests on all sections of the spacecraft, the target docking adapter, and the paraglider, from initial receiving inspection through completion of preparations for movement to the launch pad. GPO expected industrial testing to take about 90 working days, based on two full shifts of testing per day and a third shift of partial testing and partial maintenance.

  • 1963 February 28 - Successful achievement of the full burn-time duration specified for the orbit attitude and maneuver system (OAMS) 25-pound thruster. -
    Gemini Project Office reported Rocketdyne's successful achievement of the full 270-second burn-time duration specified for steady-state operation of the orbit attitude and maneuver system (OAMS) 25-pound thruster. This had been the primary focus of Rocketdyne's research effort, in line with McDonnell's position that meeting steady-state life operations with the 25-pound OAMS thrust chamber assembly (TCA) was the key to resolving major problems in the development of spacecraft liquid propulsion systems. McDonnell engineers believed that a TCA design able to meet the steady-state life performance required of the 25-pound OAMS TCA would also be adequate to meet pulse-life performance requirements, and that a satisfactory 25-pound TCA would only have to be enlarged to provide a satisfactory 100-pound TCA. They were wrong on both counts. Rocketdyne subsequently shifted its primary TCA effort to obtaining life during pulse operation for 25-pound thrusters and steady-state life operation for 100-pound thrusters.

  • 1963 March 5 - Gemini Project Office discussed with contractors the establishment of a philosophy for the final phase of the rendezvous mission. - Launch Vehicle: Atlas.
    They agreed on the following general rules: (1) when the launch was on time, the terminal maneuver would be initiated when the Agena came within range of the spacecraft's sensors, which would occur between spacecraft insertion and first apogee; (2) automatic and optical terminal guidance techniques would always back each other up, one method being selected as an objective for each mission and the other serving as a standby; (3) during early rendezvous missions, the terminal phase would be initiated by the third spacecraft apogee or delayed until the twelfth because of range radar tracking limitations; (4) for the same reason, no midcourse corrections should be made during orbits 4 through 11; (5) in case of extreme plane or phase errors, the Agena would be maneuvered to bring it within the spacecraft's maneuver capability; and (6) after such gross Agena maneuvers, the Agena orbit would be recircularized and two orbits of spacecraft catchup would precede the initiation of terminal rendezvous plan.

  • 1963 March 12 - North American let the first of three major subcontracts for the Gemini Paraglider Landing System Program to Northrop for a parachute recovery system in the amount of $461,312. -
    A $1,034,003 subcontract for the paraglider control actuation assembly went to the Aerospace Division of Vickers, Inc., Detroit, Michigan, on March 25. The third major subcontract, $708,809 for the paraglider electronic control system, was let to the Aeronautical Division of Minneapolis-Honeywell on May 13.

  • 1963 March 15 - Comparison of the military potentials of Dyna-Soar and Gemini. -
    The Secretary of Defense directed the Air Force to conduct a comparison of the military potentials of Dyna-Soar and Gemini.

  • 1963 March 19 - Chamberlin reassigned from Manager of Project Gemini. - Program: Gemini.
    James A Chamberlin was reassigned from Manager of Project Gemini to Senior Engineering Advisor to Robert R Gilruth, Director of Manned Spacecraft Center. Charles W Mathews was reassigned from Chief, Spacecraft Technology Division, to Acting Manager of Project Gemini.

  • 1963 March 20 - Qualification tests of the production prototype ablation heatshield for the Gemini spacecraft began. -
    Structural and material properties specimen tests had already shown that the shield either satisfied or exceeded the required design level.

  • 1963 March 21 - Contract with Philco Corporation to implement the Integrated Mission Control Center. - Program: Gemini.
    A contract for $33,797,565, including fixed fee, was signed with Philco Corporation, Philadelphia, Pennysylvania, to implement the Integrated Mission Control Center. Philco would provide all the flight information and control display equipment except the real-time computer complex, which was to be built and maintained by International Business Machines Corporation. Philco would also assist Manned Spacecraft Center in maintaining and operating the equipment for at least one year after acceptance. Philco had been selected from seven qualified bidders, and final contract negotiations had begun February 25, 1963.

  • 1963 April 2 - $42.638 million increase in Gemini's actual 1963 budget. -
    Testifying before the Subcommittee on Manned Space Flight of the House Committee on Science and Astronautics, D Brainerd Holmes, Director of Manned Space Flight, sought to justify a $42.638 million increase in Gemini's actual 1963 budget over that previously estimated. Holmes explained: 'This increase is identified primarily with an increase of $49.9 million in spacecraft. The fiscal 1963 congressional budget request was made at the suggestion of the contractor. The increase reflects McDonnell's six months of actual experience in 1963.' The subcommittee was perturbed that the contractor could so drastically underestimate Gemini costs, especially since it was chosen without competition because of supposed competence derived from Mercury experience. Holmes attributed McDonnell's underestimate to unexpectedly high bids from subcontractors and provided for the record a statement of some of the reasons for the change: 'These original estimates made in December 1961 by NASA and McDonnell were based on minimum changes from Mercury technology ..... As detailed specifications for subsystems performance were developed ....... realistic cost estimates, not previously available, were obtained from subcontractors. The first of these ....... were obtained by McDonnell in April 1962 and revealed significantly higher estimates than were originally used. For example: (a) In data transmission, it became necessary to change from a Mercury-type system to a pulse code modulation (PCM) system because of increased data transmission requirements, and the need to reduce weight and electrical power. The Gemini data transmission system will be directly applicable to Apollo. (b) Other subsystems have a similar history. The rendezvous radar was originally planned to be similar to ones used by the Bomarc Missile, but it was found necessary to design an interferometer type radar for low weight, small volume, and to provide the highest reliability possible. (c) The environmental control system was originally planned as two Mercury-type systems, but as the detail specifications became definitive it was apparent that the Mercury ECS was inadequate and, although extensive use of Mercury design techniques were utilized, major modifications were required.'

  • 1963 April 2 - Final contract with McDonnell for the Gemini spacecraft. - Program: Gemini.
    NASA announced the signing of a contract with McDonnell for the Gemini spacecraft. Final negotiations had been completed February 27, 1963. Estimated cost was $428,780,062 with a fixed fee of $27,870,000 for a total estimated cost-plus-fixed-fee of $456,650,062. NASA Headquarters spent two weeks on a detailed review of the contract before signing. Development of the spacecraft had begun in December 1961 under a preliminary letter contract which the final contract superseded. The contract call for a 13 flight-rated spacecraft, 12 to be used in space flight, one to be used for ground testing. In addition, McDonnell would provide two mission simulator trainers, a docking simulator trainer, five boilerplates, and three static articles for vibration and impact ground tests.

  • 1963 April 9 - George M Low, Director of Spacecraft and Flight Missions, Office of Manned Space Flight, explained to the House Subcommittee on Manned Space Flight why eight rendezvous missions were planned. -
    'In developing the rendezvous capability, we must study a number of different possible ways of conducting the rendezvous ..... For example, we can conduct a rendezvous maneuver in Gemini by purely visual or optical means. In this case there will be a flashing light on the target vehicle. The pilot in the spacecraft will look out of his window and he will rendezvous and fly the spacecraft toward the flashing light and perform the docking. This is one extreme of a purely manual system. On the opposite end of the spectrum we have a purely automatic system in which we have a radar, computer, and stabilized platform and, from about 200 or 500 miles out, the spacecraft and the target vehicle can lock on to each other by radar and all maneuvers take place automatically from that point on. We know from our studies on the ground and our simulations that the automatic way is probably the most efficient way of doing it. We would need the least amount of fuel to do it automatically. On the other hand it is also the most complex way. We need more equipment, and more equipment can fail this maneuver so it might not be the most reliable way. The completely visual method is least efficient as far as propellants are concerned, but perhaps the simplest. In between there are many possible combinations of these things. For example, we could use a radar for determining the distance and the relative velocity between the two without determining the relative angle between the two spacecraft and let the man himself determine the relative angle. We feel we must get actual experience in space flight of a number of these possibilities before we can perform the lunar orbit rendezvous for Apollo.'

  • 1963 April 29 - NASA Headquarters approved rescheduling of the Gemini flight program as proposed by Gemini Project Office (GPO). - Launch Vehicle: Atlas.
    Late delivery of the spacecraft systems coupled with the unexpectedly small number of Mercury systems incorporated in the Gemini spacecraft had forced GPO to review the flight program critically. In the revised program, the first flight was still set for December 1963 and was still to be unmanned, but it was now to be orbital rather than suborbital to flight-qualify launch vehicle subsystems and demonstrate the compatibility of the launch vehicle and spacecraft; no separation or recovery was planned. The second mission, originally a manned orbital flight, now became an unmanned suborbital ballistic flight schedule for July 1964. Its primary objection was to test spacecraft reentry under maximum heating-rate reentry conditions; it would also qualify the launch vehicle and all spacecraft systems required for manned orbital flight. The third flight, formerly planned as a manned orbital rendezvous mission, became the first manned flight, a short-duration (probably three-orbit) systems evaluation flight scheduled for October 1964. Subsequent flights were to follow at three-month intervals, ending in January 1967. Rendezvous terminal maneuvers were planned for missions 3 (if flight duration permitted) and 4, a seven-day mission using a rendezvous pod. The sixth flight was to be a 14-day long-duration mission identical to 4 except that no rendezvous maneuver missions with the Atlas-launched Agena D target vehicle. Water landing by parachute was planned for the first six flights and land landing by paraglider from flight 7 on.

  • 1963 April 30 - NASA / Department of Defense dispute over Gemini management responsibility. - Program: Gemini.
    In a NASA position paper, stimulated by Secretary of Defense McNamara's testimony on the fiscal year 1964 budget and an article in Missiles and Rockets interpreting his statements, Robert C. Seamans, Jr., NASA Associate Administrator, stressed NASA's primary management responsibility in the Gemini program. McNamara's remarks had been interpreted as presaging an Air Force take-over of Project Gemini. Seamans recognized the vital role of the Department of Defense in Gemini management and operations but insisted that NASA had the final and overall res